Operational Costs
Below is the estimated monthly cost structure for mining operations, including equipment usage, workforce, and administrative expenses.
Fuel Consumption
Excavator
2
7,040
23.39%
Mechanical Shovel
2
5,280
17.54%
Dump Truck (16m³)
5
8,800
29.24%
Water Truck
1
1,408
4.68%
Motor Grader
1
4,400
14.62%
Generator
1
2,464
8.19%
Support Vehicles
2
704
2.34%
Total
14
30,096
100%
Employee Payroll
Geologist
1
R$10,924
$1,820.67
16.82%
Mining Engineer
1
R$7,371
$1,228.50
11.35%
Mine Technician
1
R$4,233
$705.50
6.52%
Safety Technician
1
R$3,500
$583.33
5.39%
Crushing Operators
4
R$5,648
$941.33
8.70%
Security Guards
3
R$6,561
$1,093.50
10.10%
Truck Drivers
5
R$11,900
$1,983.33
18.32%
Machine Operators
4
R$13,400
$2,233.33
20.63%
General Services
1
R$1,412
$235.33
2.17%
Total
21
R$64,949
$10,824.83
100%
Operational Costs
Electricity
1
R$1,000
$166.67
0.34%
Internet
2
R$400
$66.67
0.14%
Food
1,386
R$27,720
$4,620.00
9.44%
Office Supplies
1
R$400
$66.67
0.14%
Equipment Maintenance
1
R$10,000
$1,666.67
3.40%
Fuel Consumption
30,096
R$189,303
$31,550.64
64.44%
Employee Payroll
1
R$64,949
$10,824.83
22.11%
Total Operational Costs
-
R$293,772.84
$48,962.14
100%
The BRL/USD conversion was made at 5.81, which is the price at the time of this writing.